Project Overview
Highway 5 improvements include expanding the highway from two to four lanes west from Highway 41 in Chanhassen to Downtown Victoria. The project also includes:
- Intersection improvements
- Widening the Lake Minnewashta crossing from two to four lanes
- Reconstruction of Rolling Acres Road/Bavaria Road between Interlaken and 78th Street to reduce traffic speeds and improve safety for all users
- Safety improvements for people walking, bicycling, and rolling, including an improved crossing for the Lake Minnetonka LRT Regional Trail
Preliminary design is underway. The project team will:
- Refine the design options
- Prepare final project plans/layout and seek public input
- Determine what is needed to construct the project
- Complete environmental documentation and special studies (e.g., noise analysis)
- Obtain municipal consent from all partners
Project Purpose
The Highway 5 project aligns with the vision set forth in the Arboretum Area Transportation Plan (AATP) to address the following community priorities:
- Reducing traffic congestion
- Improving safety for all users
- Enhancing walking and bicycling conditions and connections
- Respecting the environment
- Connecting local destinations
Tentative Project Schedule
- Preliminary Design: 2023-2024
- Final Design: 2024-2025
- Construction: Fall 2025-Fall 2027
Public engagement during design will occur in three phases:
- Phase 1 – Fall 2023:
- Share project status and schedule
- Share and collect input on draft concepts
- Phase 2 – Summer 2024:
- Share community feedback from Phase 1
- Share and collect input on project design, aesthetics, and environmental review
- Introduce construction staging options
- Phase 3 – Spring 2025:
- Share the final design and aesthetic elements
- Preview construction overview and what to expect
Upcoming Events
More events are anticipated this winter. Keep an eye on this webpage and subscribe to our email updates for the latest event information.
Improvement Areas
Carver County, along with project partners, is planning improvements to Highway 5 between Downtown Victoria and Highway 41 in Chanhassen. The Highway 5 Improvements Project is one of four area improvement projects resulting from the Arboretum Area Transportation Plan (AATP). The potential improvements are largely from the AATP study and have been updated since the study was completed in 2021. Many of the following recommended potential improvements have not changed since September 2023.
Past Events
Aug. 21, 2024 Public Open House
A public open house was held on Wednesday, Aug. 21 at the Minnesota Landscape Arboretum to share updated exhibits and others materials related to the schedule, funding, environmental processes, design details, preliminary construction plans, and proposed visual improvements. Below are printable copies of the exhibits as they appeared at the in person public open house:
- Highway 5 Open House Summary
- Rolling Acres Road Roundabouts FAQ
- Project overview and environmental review process (6 exhibits)
- Updated design options (10 exhibits)
- Preliminary construction plans (5 exhibits)
- Proposed visual improvements (10 exhibits)
- *Layout: Highway 5
- *Layout: Rolling Acres Rd/Bavaria Rd
- Highway 5/41 (11x17 pdf)
- Highway 5 between Rolling Acres Rd and Minnewashta Pkwy (11x17 pdf)
- Highway 5 between Kochia Ln and Commercial Ave (11x17 pdf)
- Rolling Acres Rd/Bavaria Rd (11x17 pdf)
*Please email the project team at AATPprojects@co.carver.mn.us if you need materials in an alternate format.
Minnewashta Parkway Traffic Study November 2023 Neighborhood Meeting
A meeting was held on Nov. 1, 2023, at the Chanhassen Recreation Center to present technical findings and recommendations from the Minnewashta Parkway Traffic Study. The traffic and safety analysis evaluated traffic volumes, vehicle speeds, accommodations for people walking and bicycling, and the impacts of shifting the access to Minnesota Landscape Arboretum. More than 500 postcards were mailed out to homeowners in the surrounding area. 25 Individuals attended the meeting and five comment cards were received onsite.
During the meeting, residents discussed speeding issues and traffic flow. Residents suggested solutions like installing new speed limit signs, closing Minnewashta Parkway, or directing traffic to go to Highway 41 or Rolling Acres Road. These comments will be taken into consideration as the project evolves.
If you were not able to attend, please view the presentation and submit any questions or comments to AATPprojects@co.carver.mn.us or call 952-466-5324.
Fall 2023 Public Open House
The following materials were presented at a public open house on Sept. 27, 2023. Attendees were asked to review the materials and provide feedback to the project team. All feedback received will be taken into consideration and help influence the project team as they move toward refining draft concepts and introducing construction staging options in spring 2024. If you were not able to attend, please read the summary and review the materials, then submit any questions or comments to AATPprojects@co.carver.mn.us or call 952-466-5324.
Project Email Updates
Watch for email alerts to be posted here. Sign up to receive project emails using the link in the right toolbar.